District court: enjoined Denver Water from diverting water to the reservoir, finding the violated the CWA and .
This decision ¡ Appeal
(Denver Water wins)
TL;DR
1The case involves Denver Water's plan to expand a reservoir to prevent future water shortages. Environmental groups argued that the project violated the Clean Water Act and because the of Engineers did not properly consider alternatives or climate impacts.
2The court ruled in favor of the and Denver Water, finding that the Corps adequately considered the project's purposes and reviewed alternatives in compliance with regulations.
3The key reason was that the regulation allowed the to define the project by its specific goals, which it did reasonably, and therefore the Corps's decision was not arbitrary.
Key issues
1
Did the define the project's purpose properly under environmental laws?
Holding ¡ Yes, the reasonably defined the project to include Denver Water's dual goals, which was supported by regulation.
2
Was the 's analysis of cost and climate change impacts reasonable?
Holding ¡ Yes, the considered these factors adequately, using a sound methodology and acknowledging uncertainties.
Why it matters
This decision affects how large-scale water projects must assess environmental impacts, shaping infrastructure development in areas facing water shortages.
1Denver Water wants to expand a reservoir to prevent shortages.
2Environmental groups say this violates laws on water use and pollution.
3The court must decide if the Corps followed the rules.
Did the violate environmental laws by approving the reservoir expansion?
Be the first juror
Parties
Appellant
Save The Colorado
Appellee
Graham
Roles are inferred from the case caption.
Opinion of the court
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 1
FILED
United States Court of Appeals
PUBLISH Tenth Circuit
UNITED STATES COURT OF APPEALS September 15, 2026
Christopher M. Wolpert
FOR THE TENTH CIRCUIT Clerk of Court
_________________________________
SAVE THE COLORADO; THE
ENVIRONMENTAL GROUP;
WILDEARTH GUARDIANS; LIVING
RIVERS; WATERKEEPER ALLIANCE;
SIERRA CLUB,
Petitioners - Appellees,
Nos. 25-1137, 25-1231 & 25-1299
v.
LIEUTENANT GENERAL WILLIAM H.
GRAHAM, JR., in his official capacity as
Chief of the U.S. Army Corps of
Engineers; DOUGLAS J. BURGUM, in his
official capacity as Secretary of the
Interior; PAUL SOUZA, in his official
capacity as Acting Director of the U.S. Fish
and Wildlife Service,
Respondents.
--------------------------------------------------
CITY AND COUNTY OF DENVER,
acting by and through its Board of Water
Commissioners (Denver Water),
Intervenor Respondent - Appellant.
--------------------------------------------------
26 FORMER EPA OFFICIALS; CITY OF
BOULDER; CITY OF LAFAYETTE;
CITY OF AURORA, COLORADO;
SOUTH METRO WATER SUPPLY
AUTHORITY; BOARD OF WATER
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 2
WORKS OF PUEBLO, COLORADO;
CITY OF ARVADA; CHAMBER OF
COMMERCE OF THE UNITED STATES
OF AMERICA; NATURAL RESOURCES
LAW PROFESSORS,
Amici Curiae.
_________________________________
Appeal from the United States District Court
for the District of Colorado
(D.C. No. 1:18-CV-03258-CMA)
_________________________________
Kyle Glynn, Attorney, (Adam R.F. Gustafson, Principal Deputy Assistant Attorney
General, and Robert N. Stander, Deputy Assistant Attorney General, with him on the
briefs), Environment and Natural Resources Division, United States Department of
Justice, Washington, DC, for Federal-Appellants.
Amanda Shafer Berman, Crowell & Moring LLP, Washington, DC (Elizabeth B. Dawson
and Tara M. Derbisz, Crowell & Moring LLP, Washington, DC; and Jessica R. Brody
and Crystal J. Easom, Denver Water, Denver, Colorado) with her on the briefs, for
Intervenor-Appellant.
William S. Eubanks II (Matthew R. Arnold with him on the briefs), Eubanks &
Associates, PLLC, Washington, DC, for Petitioners-Appellees.
Dulcinea Z. Hanuschak, Steven O. Sims, and Katherine J. Duncan, Brownstein Hyatt
Farber Schreck, LLP, Denver, Colorado; Gabriel Racz, Clark Hill PLC, Boulder,
Colorado; and Karl Ohlsen, Carlson, Hammond & Paddock, L.L.C., Denver, Colorado,
filed an Amici Curiae Brief on behalf of the City of Aurora, Colorado, South Metro
Water Supply Authority, and the Board of Water Works of Pueblo, Colorado, in Support
of Intervenor-Respondent-Appellant, the City and County of Denver, and Reversal of the
District Courtâs Decision.
Steven P. Jeffers, Attorney for Amicus Party, City of Arvada, Lyons Gaddis, PC,
Louisville, Colorado, filed an Amicus Curiae Brief on behalf of the City of Arvada in
Support of Appellant Denver Waterâs Opening Merits Brief.
Andrew R. Varcoe and Stephanie A. Maloney, United States Chamber Litigation Center,
Washington, DC and Jeremy C. Marwell, Counsel of Record, and Adam Kleven, Vinson
& Elkins LLP, Washington, DC, filed an Amicus Curiae Brief on behalf of the Chamber
of Commerce of the United States of America in Support of Appellants and Reversal.
2
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 3
Cale Jaffe, Director, Environmental Law & Community Engagement Clinic, University
of Virginia School of Law, Charlottesville, Virginia, filed an Amici Curiae Brief on
behalf of 26 Former EPA Officials.
Sarah A. Matsumoto, Getches-Green Natural Resources, Energy, and Environmental Law
Clinic, University of Colorado Law School, Boulder, Colorado, filed an Amici Curiae
Brief on behalf of Natural Resources Law Professors in Support of Petitioners-Appellees
and Affirmance.
Teresa Taylor Tate, City Attorney, Luis A. Toro, Senior Counsel, and Jessica L. Pault-
Atiase, Senior Counsel, City of Boulder, Boulder, Colorado; Erin E. Poe, Deputy City
Attorney, City of Lafayette, Lafayette, Colorado; and David F. Bower, Johnson &
Repucci LLP, Louisville, Colorado, filed an Amici Curiae Brief on behalf of the City of
Boulder and City of Lafayette in Support of Appellant City and County of Denver
Supporting Reversal.
_________________________________
Before HOLMES, Chief Judge, TYMKOVICH, and MORITZ, Circuit Judges.
_________________________________
TYMKOVICH, Circuit Judge.
_________________________________
In 2002, Denver Water predicted it would soon face a water shortage. To
address this problem, it proposed the Moffat System Collection Project, which would
increase the holding capacity of the Gross Reservoir (a large reservoir northwest of
Boulder) by raising the height of the Gross Dam. Since the proposal would affect
wetlands at the base of the dam structure, Denver Water applied for the necessary
wetlands permit from the Army Corps of Engineers in 2003. And after an extensive
process, the Corps issued the permit in 2017. In 2026, Denver Water completed a
3
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 4
$600,000,000 construction project 1 that raised the Gross Dam 131 feet, and the
Reservoir stands ready to hold an additional 77,000 acre-feet of water.
But Denver Water cannot fill the Reservoir. Save the Colorado and other
environmental groups sued the Corps for violating the Clean Water Act and the
National Environmental Protection Act (NEPA), alleging deficiencies in the Corpsâs
fourteen-year review process. The district court agreed and enjoined Denver Water
from diverting water to the Reservoir.
Exercising jurisdiction under 28 U.S.C. § 1291, we reverse. The district court
found that the Corps violated the CWA and NEPA because it (1) too narrowly
defined the Moffat Projectâs purpose, and (2) failed to adequately consider project
costs and climate changeâs impact on the projectâs feasibility. We conclude the
Corps may include a projectâs multiple related purposes when defining the projectâs
purpose. And we also find that the Corpsâs determinations on cost and climate
change were reasonable and supported by the record. 2
1
The record shows that the project cost around $600,000,000, but counsel for
the Environmental Groups represented at oral argument that the project has cost over
$800,000,000.
2
Denver Water moved to expedite these consolidated appeals. See Doc. 139,
25-1137; Doc. 118, 25-1231; Doc. 103, 25-1299. We grant the motion.
4
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 5
I. Background
We begin with a brief description of the Moffat Project and then discuss the
regulatory framework governing this appeal. Next we recount the Corpsâs review
process, and finally, we chronicle the lengthy history of this litigation.
A. Denver Waterâs Proposed Project
Denver Water is a municipal water utility. Its infrastructure comprises two
delivery systems: the North System (the Moffat Collection System) and the South
System. These two systems are not connected. The Moffat System serves 10% of
Denver Waterâs customers; the South System, 90%. The following map shows the
systemsâ relative sizes.
5
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 6
App. 224.
6
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 7
In 2002, Denver Water hired a consulting group, BBC Research and
Consulting, to update Denver Waterâs water management plan. The group issued a
â2002 IRP demand forecast,â which predicted that the demand of Denver Waterâs
customers would exceed Denver Waterâs water supply by 2016. Denver Water also
feared that its water system faced a different vulnerability: overreliance on the South
System. This overreliance left Denver Water (and its customers) vulnerable to a
water shortage if the South System was taken offlineâbecause of a natural disaster,
malfunction, or otherwise.
To prevent a future water shortage, Denver Water proposed an expansion of
the Gross Reservoir, a dammed reservoir northwest of Denver that was built in 1954.
The Expansion would raise the Gross Dam by 131 feet, increasing the holding
capacity of the Reservoir. Denver Water could then fill the additional capacity by
diverting water from the Fraser River and Williams Fork River on the Rocky
Mountainâs Western Slopeâpart of the Colorado Riverâs drainage basinâthrough
the Moffat Tunnel, a tunnel that cuts through the mountains near the Winter Park ski
area.
Raising the Gross Dam would require placing a new foundation at the base of
the dam expansion. The location for that new foundation would be in South Boulder
Creekâthe stream at the foot of the existing Gross Dam. Placing fill in that location
required a permit from the Army Corps of Engineers. So before Denver Water could
7
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 8
move forward with the Gross Reservoir Expansion, it needed to secure a fill permit
from the Corps.
B. Regulatory Framework
The Clean Water Act regulates water pollution in the United States by
prohibiting âthe discharge of any pollutantâ except as authorized by the Act. See 33
U.S.C. § 1311(a). The Act defines âpollutantâ broadly. The term encompasses not
only conventional contaminants, like âsewage sludgeâ and âchemical wastes,â but
also ârock,â âsand,â and âcellar dirt.â 33 U.S.C. § 1362(6). Thus, any project (like
Denver Waterâs proposed project) that plans to discharge âdredge or fill material
intoâ the waters of the United States must obtain a permit, called a § 404(b) permit.
33 U.S.C. § 1344(b). The § 404(b) permitting process is guided by the § 404(b)
regulations, which are promulgated by the EPA. The key § 404(b) regulation hereâ
40 C.F.R. § 230.10âallows the permit to issue only if the proposed action is the least
environmentally damaging practicable alternative (the LEDPA). 40 C.F.R.
§ 230.10(a). 3 Applying that language here, the Corps could issue Denver Waterâs
3
The relevant portion of the regulation reads in full: âno discharge of dredged
or fill material shall be permitted if there is a practicable alternative to the proposed
discharge which would have less adverse impact on the aquatic ecosystem, so long as
the alternative does not have other significant adverse environmental consequences.â
40 C.F.R. § 230.10(a).
8
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 9
permit only if no alternative project existed that was both practicable and less
environmentally damaging than Denver Waterâs proposed project.
Section 230.10(a)(2) explains how the Corps must assess practicability. âAn
alternative is practicable if it is available and capable of being done after taking into
consideration cost, existing technology, and logistics in light of overall project
purposes.â 40 C.F.R. § 230.10(a)(2) (emphasis added). The Environmental Groupsâ
challenge focuses on the italicized portions of the regulation.
The § 404(b) Regulations also assign a standard of proof. By default, the
Corps must determine that the proposed action is the least environmentally damaging
practicable alternative. But if the project is non-water dependent, 4 then the Corps
bears a heavier burden; it must clearly demonstrate that the proposed project is the
LEDPA. As the § 404(b) Regulations put it, âpracticable alternativesâ that are less
environmentally damaging are âpresumed to be available, unless clearly
demonstrated otherwise.â 40 C.F.R. § 230.10(a)(3). The parties here agree that
Denver Waterâs project is non-water dependent and that the Corps needed to clearly
demonstrate that Denver Waterâs proposed project was the LEDPA.
In addition to the CWA, the National Environmental Policy Act imposes
certain procedural requirements on federal agencies before they may âbuil[d], fund[],
or approve[]â âcertain infrastructure projects.â Seven Cnty. Infrastructure Coal. v.
4
A project is non-water dependent if its âbasic purposeâ can be achieved
without âaccess or proximity to or siting within the special aquatic site in question.â
40 C.F.R. § 230.10(a)(3).
9
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 10
Eagle County, 605 U.S. 168, 172 (2025). NEPAâs procedural obligations arise for
âmajor Federal actions,â 42 U.S.C. § 4332(c), and the Corpsâs issuance of a § 404(b)
permit is a major federal action. Thus, before issuing a § 404(b) permit, the Corps
must typically prepare an Environmental Impact Statement (EIS), 5 which âmust
address the significant environmental effects of a proposed project and identify
feasible alternatives that could mitigate those effects.â Seven Cnty., 605 U.S. at 172.
Relevant here, the EIS must evaluate âa reasonable range of alternatives to the
proposed agency action . . . that are technically and economically feasible, and meet
the purpose and need of the proposal.â 42 U.S.C. § 4332(c)(iii). The EIS
requirement imposes no substantive standards; it is meant only âto inform agency
decisionmaking, not to paralyze it.â Seven Cnty., 605 U.S. at 173.
C. The Corpsâs Permitting Process
In 2003, the Corps began consideration of Denver Waterâs application for a
§ 404(b) permit. After a comprehensive review that included its use of in-house
5
If an agency determines that the proposed project will not âsignificantly
affect[] the quality of the human environment,â it does not need to issue an EIS; it
instead issues a finding of no significant impact. 42 U.S.C. § 4332(c)(iii); Depât of
Transp. v. Pub. Citizen, 541 U.S. 752, 757â58 (2004).
10
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 11
experts and outside consultants, the Corps approved the application and issued the
permit in 2017.
During that fourteen-year evaluation, the Corps underwent a multi-step
analysis of Denver Waterâs application. In broad outline, the processâs timeline
looks like this:
⢠in 2003, the Corps issued a scoping notice and summary
⢠in 2009, the Corps released the draft EIS
⢠in 2014, the Corps published its final EIS, and
⢠in 2017, the Corps issued its record of decision (ROD) and granted
Denver the permit.
At each step, the Corps explained its decision. The Final EIS alone spanned
ten volumes, and the full record stretched to nearly 200,000 pages. And at each step
the Environmental Groups took issue with the Corpsâs analysis of the alternatives to
Denver Waterâs proposed project. Throughout the process, the Environmental
Groups identified the following primary deficiencies: (1) the Corps defined the
proposed projectâs purpose too narrowly, causing the Corps to exclude practicable
alternatives that could meet the projectâs general purpose; (2) the Corps failed to
adequately measure the costs of the proposed project and the alternatives; and (3) the
11
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 12
Corps failed to account for climate changeâs effects on the feasibility of Denver
Waterâs proposed project.
1. Scoping Notice and Summary
Once Denver Water applied for a permit, the Corps issued a scoping notice in
September 2003. The scoping notice is an agencyâs first step in taking agency action
under NEPA and the CWA. The scoping process determines what needs the
proposed action will target and what alternatives should be considered.
The notice listed two primary needs: (1) to increase the firm yield in the
Moffat Collection System and (2) correct imbalances in the Moffat and South
systems. Denver Water proposed to meet those needs by increasing the capacity of
Gross Reservoir, which would allow Denver Water to meet future water needs by
diverting more water from the Fraser River and the Williams Fork River, and to
better allocate available water from the Moffat and South systems to control for and
improve the ability of the Moffat system to provide reliable water delivery in the
future.
Environmental groups objected to the Corpsâs combining both needs together.
They wanted them considered separately, so that more alternatives to a dam would be
practicable. For example, one proposed project was âConduit X,â which would
bridge the Moffat System and the South System by a pipeline. That would satisfy the
need to correct imbalances in the system but not the need to increase firm yield.
In December 2003, the Corps issued a scoping summary, agreeing with Denver
Water that the agency action should solve both the firm-yield and imbalance issues.
12
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 13
The scoping summary breaks the imbalance issue into three subpartsâensuring
âreliabilityâ of the Moffat System; fixing the âvulnerabilityâ of the entire system due
to overreliance on the South System; and adding âflexibilityâ to shift water-delivery
burdens to the Moffat System. App. 1490.
2. Draft EIS
Following the scoping process, the Corps began the EIS review of Denverâs
proposed project in December 2003. The Corps decided to prepare an EIS that would
satisfy the reviews required by both the CWA and NEPA, rather than performing
separate analyses. The Corps was the lead agency responsible for preparing the EIS,
though input was also provided by other cooperating agencies that would approve
various components of Denver Waterâs proposed project. These cooperating
agencies were the EPA, FERC, the Colorado Department of Public Health and
Environment, and the Colorado Department of Natural Resources.
In October 2009, the Corps released the Draft EIS. The Draftâs purpose-and-
need statement included both the firm-yield and imbalance purposes. The statement
defined the projectâs purpose as âdevelop[ing] 18,000 acre-feet per year of new,
annual firm yield to the Moffat Treatment Plant and raw water customers upstream of
the Moffat Treatment Plant pursuant to the Board of Water Commissionersâ
commitment to its customers.â App. 1145.
The Draft then detailed the Corpsâs alternatives analysis. The analysis began
with a screening process, which proceeded in two stages. First, the Corps screened
303 alternative proposals based on âPurpose and Need, existing technology, logistics,
13
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 14
costs, and environmental consequences.â App. 1173. That initial screening removed
possible water sources and components that were ânot capable of meetingâ the
projectâs purpose; so an alternative was excluded if it could not (1) âprovide new
firm yield,â (2) âsupply water to Moffat Collection System,â or (3) âproduce a
solution within the necessary . . . timeframe.â App. 1150. The second criterion was
one of the more âsignificant criteria used to eliminateâ alternative proposals. Id.
Next, the initial screening excluded alternative proposals based on their
relative costs. To estimate a projectâs expected total cost, which the Corps called the
projectâs ârelative development costâ (RDC), the Corps added together the projectâs
expected capital costsâcalled the ârough order of magnitudeâ (ROM)âand the
projectâs estimated contingent costs. The capital costs included expenditures on the
projectâs infrastructureâcomponents like âsurface storage components,â pipelines,
pump stations, and âwater treatment facilities,â App. 1161âwhile the contingent
costs included expenditures like â[l]and acquisition,â â[p]redesign and design
engineering,â and â[l]egal and financial services.â App. 1366. The Corps estimated
that a projectâs contingent costs would amount to 50% of the capital costs, so it
applied a 50% multiplier to the projectâs capital costs in order to estimate the
projectâs total cost. The Corps explained that using this formula produced âa more
representative cost estimate that is suitable for use in comparing alternatives.â App.
1161. Having excluded alternative proposals based on their inability to satisfy the
14
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 15
projectâs purpose and their costs, the Corpsâs initial screening left 34 projects for
consideration.
Second, the Corps screened the remaining projects based on their
âenvironmental consequences to the aquatic environment, other ecosystems, and
other natural environmental values.â App. 1164. This second step left five
alternative projects that the Corps would analyze more extensively in the EIS. Id.
The Corps also discussed how climate change could impact Denver Waterâs
proposed project. The Corps observed that some scientific studies have predicted
that climate change will cause stream flow to âpeak earlierâ and to diminish in
quantity because of increased âevapotranspirationâ and longer droughts. App. 1213.
These changes to streamflow, the Corps noted, could affect Denver Waterâs ability to
divert water to an expanded Gross Reservoir. If the streamflow volume diminishes,
then the amount of water that Denver Water can divert will be limited. And if the
streamflow peaks earlier, then the water levels may not peak when Denver Water has
priority rights, preventing it from diverting the water to the Gross Reservoir. As the
Corps put it, climate changeâs effect on stream flow could âdecrease Denver Waterâs
[firm] yield.â App. 1213.
Though the Corps discussed climate changeâs effects, it did not quantify or
model the effects on stream flow. The Corps explained why: âthere is no accepted
15
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 16
scientific method of transforming the general concept of increasing temperatures into
incremental changes in stream flow or reservoir levels.â App. 1213.
The Draft elicited extensive public comment. The EPA, for example, objected
to the Draftâs purpose-and-need statement because it incorporated several
âunderlying project proponent needs,â which excluded âalternatives that may
otherwise be âpracticableâ considering the basic/overall project purposeâ of
increasing water supply. App. 1061. Other comments criticized the Corpsâs cost
methodology because it employed â[b]road assumptionsâ rather than more
particularized estimates. App. 1069. Still more comments took issue with the
Corpsâs choice not to quantify the effects of climate change on stream flows, given
the existence of a model showing that âfirm yield decreased between 7% and 14%
with increases in temperature of 2 to 5 degrees Fahrenheit.â App. 1073.
3. Final EIS and ROD
The Corps published its Final EIS five years later in April 2014. The Final
EIS was substantially similar to the Draft, but it added some information in response
to the public comments. In response to the EPAâs comment about the purpose-and-
need statement, the Corps justified incorporating Denver Waterâs multiple needs into
one purpose because âthe multiple needs . . . are not âindependentâ but rather are
interconnected in the water supply issues that Denver Water is facing.â App. 1059.
The Corps defended its cost methodology by pointing out that it calculated the 50%
multiplier based on â[c]omparisons . . . with other projects for which planning-level
cost estimates have been prepared,â and also had its âthird-party consulting team
16
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 17
ma[k]e comparisons with other projects.â App. 1070. Finally, the Corps rejected
streamflow models proposed by the comments because âthere is a considerable
amount of uncertainty inherent in the various climate and hydrology models and
associated input data set used inâ the study. App. 1075.
After issuing the Final EIS, the Corps published its Record of Decision (ROD)
in July 2017. The ROD concluded that the EIS satisfied NEPA and incorporated its
findings. App. 437â38. The ROD also found that Denver Waterâs proposed project
was the least environmentally damaging practicable alternative. Having made those
findings, the Corps issued Denver Waterâs § 404(b) permit in August 2017.
Denver Water then secured the necessary permitting from other agencies, and
with those permits in hand, Denver Water began construction in 2022 to raise the
Gross Dam and expand the Gross Reservoir, completing major construction in 2026.
But Denver Water has yet to clear the trees surrounding the Reservoir and to divert
water to fill the Reservoirâs newly increased capacity.
D. The Litigation
Save the Colorado and other Environmental Groups sued the Corps in
December 2018. Denver Water intervened a few months later. The Environmental
Groups alleged violations of the CWA and NEPA. 6 They first alleged that the Corps
violated the CWA by issuing Denver Waterâs permit without clearly demonstrating
6
The Environmental Groups also brought a challenge under the Endangered
Species Act against the Department of the Interior and the United States Fish and
Wildlife Service. The district court dismissed that claim, and the Environmental
Groups do not appeal that decision.
17
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 18
that Denver Waterâs proposed project was the LEDPA. The Environmental Groups
alleged three errors with the Corpsâs LEDPA determination: (1) the Corps defined the
projectâs purpose too narrowly, which resulted in excluding otherwise practicable
alternatives; (2) the Corpsâs cost methodology was not particularized to each project;
and (3) the Corps failed to adequately evaluate climate changeâs effects on stream
flows. The Environmental Groupsâ NEPA challenge is similar. They alleged that the
Corps acted arbitrarily by (1) defining the EISâs purpose-and-need statement too
narrowly, (2) failing to accurately estimate project costs, and (3) choosing not to
conduct a quantitative analysis of climate changeâs effects on stream flow.
As a remedy, the Environmental Groups sought (1) a declaration that the Corps
violated the CWA and NEPA; (2) vacatur of the Final EIS, the ROD, and Denver
Waterâs § 404(b) permit; and (3) an injunction stopping the Corps âfrom taking any
further actions in furtherance of this project untilâ the Corps âcomplied with federal
law.â App. 104. They did not seek a temporary restraining order or seek other
emergency or interim relief.
The district court held a hearing on the petition in September 2024. 7 The court
agreed with the Environmental Groups and found that the Corps had violated both the
7
The tortuous history of this litigation explains the six-year span between the
Environmental Groupsâ initial filing and the district courtâs ruling. Two years
elapsed before the Environmental Groups filed a supplemental petition for review in
2020. The Corps and Denver Water moved to dismiss the petition for lack of
jurisdiction, which the district court granted. The court reasoned that the courts of
appeals have exclusive jurisdiction over challenges to FERC decisions, and because
the Environmental Groups challenged FERCâs approval of Denver Waterâs amended
license, the suit had to be brought in the circuit. We disagreed, finding the
18
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 19
CWA and NEPA. The court found that the Corpsâs analysis failed to clearly
demonstrateâas required by 40 C.F.R. § 230.10(a)âthat Denver Waterâs proposed
project was the LEDPA for the reasons identified above. The court further found the
EIS did not comply with NEPA for substantially the same reasons. After deciding
for the Environmental Groups on the merits, the court postponed ruling on the issue
of remedy.
The court later issued its first remedies order. The court ordered vacatur and
remand of the Final EIS, the ROD, and Denver Waterâs § 404(b) permit; it also
permanently enjoined âenlargement of the Gross Reservoir, including tree removal,
water diversion, and impacts to wildlife.â App. 361â62. And because construction
of the dam was partially complete at the time, the court preliminarily enjoined further
construction of the dam pending a hearing on what additional construction would be
necessary to ensure the damâs structural integrity.
The court then issued its second remedies order. The court concluded that
public safety required Denver Water to finish constructing the dam, so it vacated its
Environmental Groups attacked the Corpsâs issuance of the fill permit, not FERCâs
approval of the license. Save the Colorado v. Spellmon, 50 F.4th 954, 971 (10th Cir.
2022). We thus reversed the dismissal and remanded to the district court for further
proceedings. On remand, the parties submitted extensive briefing and a voluminous
administrative record, all requiring a lengthy review.
19
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 20
preliminary injunction against further dam construction. But the court left intact its
prior permanent injunction and remand with vacatur.
Denver Water appealed from the first remedies order and the courtâs final
judgment, and the Corps appealed from the final judgment. We consolidated these
three appeals for argument and disposition. 8
II. Discussion
The Corps and Denver Water argue the district court erred by finding CWA
and NEPA violations based on the three alleged deficiencies identified above.
8
A prior panel of this court identified a possible jurisdictional defect in
Denver Waterâs appeal from the final judgment belowânamely, that the judgment is
not final under the administrative-remand rule. The administrative-remand rule
usually applies when (1) the challenged agency action is adjudicative and (2) the
district court remands to the agency for further proceedings. See Rocky Mountain
Wild v. Dallas, 98 F.4th 1263, 1283 (10th Cir. 2024). The first requirement is met
here. See id. at 1283â84 (finding that an agencyâs issuing an ROD on a right-of-way
application was adjudicative); W. Energy All. v. Salazar, 709 F.3d 1040, 1048 (10th
Cir. 2013) (â[A]gency permitting âfalls closer to the traditional concept of
adjudication . . . .ââ (quoting New Mexico ex rel. Richardson v. Bureau of Land
Mgmt., 565 F.3d 683, 699 n.17 (10th Cir. 2009))). The second, however, presents a
closer question since it is unclear whether the district courtâs order âremand[ing] with
vacaturâ required the Corps to conduct any further proceedings. App. 361.
But even assuming the administrative-remand rule applies, we nevertheless
conclude that the practical-finality exception to the rule allows the appeal to proceed.
â[W]e have applied the practical finality rule to review important legal questions
which a remand may make effectively unreviewable.â Rocky Mountain Wild, 98
F.4th at 1284 (citation modified). This can occur âwhen an agency was directed to
implement a particular outcome rather than recommence a proceeding.â Id. (citing
Ausmus v. Perdue, 908 F.3d 1248, 1252 (10th Cir. 2018)). Such is the case here
where the district court permanently enjoined âenlargement of the Gross Reservoir,
including tree removal, water diversion, and impacts to wildlife.â App. 362. Even if
the district courtâs remand directed the Corps to redo its EIS and permitting process,
the agency would still be permanently enjoined from authorizing Denver Water to
complete the Project and would be without an avenue for appellate review.
20
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 21
Denver Water also argues the case is both constitutionally and prudentially moot
because the activity authorized by the § 404(b) permitâdischarging fill at the foot of
the damâis complete, so this court is powerless to remedy the Environmental
Groupsâ injuries.
We find that this case is not constitutionally moot because a remand back to
the Corps could still partially remedy the Environmental Groupsâ injuries: the Corps
could impose additional mitigation measures or other special conditions. And we
need not address prudential mootness because we find the Environmental Groupsâ
claims fail on the merits. The touchstone for judicial review of agency action is
deference, and nowhere is deference more appropriate than when an agency exercises
its expertise to make technical and scientific judgments. The Corpsâs three
determinationsâwhich the district court found arbitrary and capriciousâfall easily
within that zone of discretion, and none of those determinations were arbitrary or
capricious.
A. Mootness
We review de novo the issue of constitutional mootness. Rio Grande Silvery
Minnow v. Bureau of Reclamation, 601 F.3d 1096, 1109 (10th Cir. 2010). Courts may
exercise judicial power only over âcasesâ or âcontroversies.â U.S. Const. art. III,
§ 2. To satisfy that case-or-controversy requirement, a plaintiff must have standing
to sue, which in turn requires that the plaintiffâs injury be redressable by a favorable
judicial decision. Audubon of Kan., Inc. v. U.S. Depât of Interior, 67 F.4th 1093,
1102 (10th Cir. 2023). The injury must remain redressable throughout the litigation;
21
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 22
if, through intervening circumstances, the court can no longer redress the plaintiffâs
injury, the case is moot. Id. Thus, the key question for mootness is âwhether
granting a present determination of the issues offered will have some effect in the
real world.â Rio Grande Silvery Minnow, 601 F.3d at 1110 (quoting Wyoming v. U.S.
Depât of Agric., 414 F.3d 1207, 1212 (10th Cir. 2005)). The party asserting mootness
bears the burden of showing mootness. WildEarth Guardians v. Pub. Serv. Co. of
Colo., 690 F.3d 1174, 1183 (10th Cir. 2012).
The mootness requirement applies equally to the alleged NEPA and CWA
violations here. See Caddo Nation of Okla. v. Wichita & Affiliated Tribes, 877 F.3d
1171, 1176â77 (10th Cir. 2017). âThese claims ordinarily no longer present[] a live
controversy when the proposed action has been completed and when no effective
relief is available.â Id. (quoting Airport Neighbors All., Inc. v. United States, 90 F.3d
426, 428 (10th Cir. 1996)). But even if full relief is no longer available, partial relief
will still save a case from being moot. Id. Thus, âcourts still consider NEPA claims
after the proposed action has been completed when the court can provide some
remedy if it determines that an agency failed to comply with NEPA.â Airport
Neighbors, 90 F.3d at 428â29. For example, if a court can enjoin use of a project
until the agency reevaluates the project, the case is not mootâeven if the projectâs
construction is complete. Id.; see also Sierra Club v. U.S. Army Corps of Engârs, 803
F.3d 31, 43 (finding a NEPA case not moot because âan order wholly or partly
22
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 23
enjoining operation of the pipeline, pending further analyses of the pipelineâs
environmental impact, would provideâ partial relief).
The Environmental Groups allege two main injuries: (1) procedural harm from
the Corpsâs uninformed decision making, and (2) aesthetic, recreational, and
scientific harms from a further depleted Colorado River and construction at the
Reservoir. See App. 43â49; Wockner Decl., Dkt. No. 134-1; Kurtz Decl., Dkt. No.
134-2.
We find those injuries could be partially remedied by a remand back to the
Corps for further consideration. On remand, the Corps could, for example, require
Denver Water to take additional mitigation measures. See Hillsdale Envât Loss
Prevention, Inc. v. U.S. Army Corps of Engârs, 702 F.3d 1156, 1167 (10th Cir. 2012)
(explaining that ânew information revealedâ and considered on remand âcould
motivate the Corps to revise its decisionâ and order âadditional mitigationâ). Those
additional mitigation measures could offset the aesthetic, recreational, and scientific
harms alleged by the Environmental Groups. Moreover, the Corps might strengthen
the special conditions already in the permitâfor example, the condition that Denver
Water âkeep the use of machinery in the waterway to a minimumâ and âprevent any
petroleum products, chemicals, or other deleterious materials from entering the
water.â App. 313. Those conditions could ensure that any further work Denver
Water performs to complete the project does not harm jurisdictional waters. The
ability of the Corps to impose additional mitigation or special conditions keeps this
case live, even if the Corps no longer can conduct a meaningful alternatives analysis.
23
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 24
Hillsdale, 702 F.3d at 1167 (finding partial relief available because the Corps could
impose additional mitigation after conducting a proper NEPA analysis); Sierra Club,
803 F.3d at 43.
Unlike constitutional mootness, prudential mootness derives from the courtâs
remedial discretion. Winzler v. Toyota Motor Sales U.S.A., Inc., 681 F.3d 1208, 1210
(10th Cir. 2012). Though constitutional and prudential mootness overlap, prudential
mootness poses a different question: whether âthe anticipated benefits of a remedial
decree no longer justify the trouble of deciding the case on the merits.â Id. Denver
Water argues this case is prudentially moot, even if it is not constitutionally moot.
But because we find that the Environmental Groupsâ CWA and NEPA claims fail on
the merits, we need not address prudential mootness. Sierra Club, Inc. v. Bostick,
787 F.3d 1043, 1047 n.4 (10th Cir. 2015)).
B. Merits
We review the Environmental Groupsâ CWA and NEPA claims under the
APAâs deferential arbitrary-and-capricious standard. 9 An agency acts arbitrarily
when it (1) âentirely fail[s] to consider an important aspect of the problem,â (2)
âoffer[s] an explanation for its decision that runs counter to the evidence before the
agency, or is so implausible that it could not be ascribed to a difference in view or the
9
The Environmental Groups brought their claims under the APA, alleging the
Corpsâs decision to issue the permit was âarbitrary, capricious, an abuse of
discretion, or otherwise not in accordance with lawâ because the decision was
arbitrary and violated the CWA and NEPA.
24
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 25
product of agency expertise,â (3) âfail[s] to base its decision on consideration of the
relevant factors,â or (4) âma[kes] âa clear error of judgment.ââ Am. Wild Horse
Campaign v. Raby, 144 F.4th 1178, 1188 (10th Cir. 2025) (quoting Richardson, 565
F.3d at 704)).
In the context of a CWA claim, arbitrary-and-capricious review has an
additional feature when the non-water-dependent presumption applies. The inquiry
shifts to asking whether it was arbitrary and capricious for the Corps to find that it
had clearly demonstrated that Denver Waterâs proposed project was the LEDPA. We
do not ask, in the first instance, whether we think the Corps clearly demonstrated the
proposed project was the LEDPA. See Hillsdale, 702 F.3d at 1166. 10 To clearly
demonstrate an alternative should be excluded, the Corps need only take âa hard look
at the proposals and reach[] a meaningful conclusion based on the evidence.â Id. In
the context of a NEPA claim, arbitrary-and-capricious review carries even more
deference. Seven Cnty., 605 U.S. at 180 (requiring âsubstantial deference to the
agencyâ when reviewing for compliance with NEPA).
1. Project Purpose
The Corpsâs definition of the Moffat Projectâs purpose was neither arbitrary
nor capricious. Recall that 40 C.F.R. § 230.10(a)(2) instructs the agency to evaluate
practicability in light of âoverall project purposes.â And the regulations apply the
10
The district court seemed at times to lose sight of this distinction. See, e.g.,
App. 272 (finding âthe Corps has not met its burden of âclearlyâ demonstrating that
the Proposed Action is the LEDPAâ because the Corps âfail[ed] to prove the
financial feasibility of the Proposed Actionâ).
25
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 26
non-water-dependent presumption if the project does not need to impact
jurisdictional waters âto fulfill its basic purpose.â § 230.10(a)(3). The Corps assigns
these phrases independent meaning. The Corps views a projectâs âbasic purposeâ as
its âfundamental, essential, or irreducible purpose.â App. 410. The Corps
determined that the Moffat Projectâs basic purpose is âto provide supplemental water
supply,â and it accordingly applied the non-water dependent presumption. But the
Corps understands âoverall project purposesâ as âmore specifically describ[ing] the
applicantâs goals for the [p]roject.â App. 411. The Corps defined the Moffatâs
overall purposes as âdevelop[ing] 18,000 [acre feet per year] of new, firm yield to the
Moffat Treatment Plant and raw water customers upstream of the Moffat Treatment
Plant.â App. 411. This formulation incorporated Denver Waterâs dual goals of
increasing water supply and correcting overreliance on the South System.
The Environmental Groups argue that § 230.10(a) uses âoverall project
purposesâ and âbasic purposeâ interchangeably. To the Environmental Groups, the
phrases mean the same thing: the single, most general purpose the project aims to
achieve. And, the Environmental Groups argue, because the Corps defined the
Moffat Projectâs basic purpose as increasing water supply, the Corps had to define
the projectâs overall project purposes as increasing water supply; it could not define
them according to Denver Waterâs two underlying purposesâto increase water
supply and to correct overreliance on the South System.
The regulationâs text does not support the Environmental Groupsâ cramped
view of a projectâs overall purposes. âOverall project purposesâ unambiguously
26
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 27
allows the Corps to assess a projectâs multiple, related goals; not simply the projectâs
most general purpose. First, the regulationâs text unambiguously gives the terms
independent meaning. Start with the presumption that different language implies
different meaning. See Antonin Scalia & Bryan A. Garner, Reading Law, 170â72
(2012). And the dictionary defines âbasicâ and âoverallâ differently. Compare
Basic, Am. Heritage Dictionary (5th ed. 2022) (â[a]n essential, fundamental element
or entity.â); Basic, Websterâs New Collegiate Dictionary (1979) (âof, relating to, or
forming the base or essence,â âconstituting or serving as the basis or starting pointâ);
with Overall, Am. Heritage Dictionary (5th ed. 2022) (âIncluding everything;
comprehensiveâ). But whatever might be said about the difference between âoverallâ
and âbasic,â the text uses the pluralââoverall project purposes.â § 230.10(a)(2).
The plural construction supports reading the phrase to encompass several different
purposes, rather than one single gist of the project. See Del. Riverkeeper Network v.
U.S. Army Corps of Engârs, 869 F.3d 148, 157â158 (3d Cir. 2017); Friends of Santa
Clara River v. U.S. Army Corps of Engârs, 887 F.3d 906, 912 (9th Cir. 2018).
Context also supports our reading. The regulation uses âbasic purposeâ to
assess whether the project is water dependent. 40 C.F.R. § 230.10(a)(3). So the
Corps only needs a very general idea of what the projectâs purpose is; it just needs to
decide whether the project must discharge fill into the proposed aquatic site (e.g.,
building a dock) or not. But the Corps assesses the projectâs overall purposes to
evaluate alternatives, an evaluation that calls for a more specific understanding of
what the project is meant to achieve. See Greater Yellowstone Coal. v. Flowers, 359
27
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 28
F.3d 1257, 1270 (10th Cir. 2004) (recognizing the Corps âhas a duty to take into
account the objectives of the applicantâs projectâ in the alternatives analysis (quoting
Sylvester v. U.S. Army Corps of Engârs, 882 F.2d 407, 409 (9th Cir. 1989))).
The Environmental Groups suggest that § 230.10(a)(2)âs use of both âoverall
project purposesâ and âbasic purposeâ in the practicability subsection implies they
are interchangeable. Apparently, under their view, the EPA did not mean to give
âoverall project purposesâ independent meaning; it just wanted a synonym for âbasic
purpose.â In any event, the Environmental Groupsâ argument overlooks the
presumption that different language implies different meaning, and indeed, the
phrasesâ proximity more strongly suggests the regulation envisions their different
meanings. If the EPA did not want the Corps to consider multiple âoverall project
purposesâ in the practicability analysis, it could have used the phrase near at hand:
âbasic purpose.â It did not, and we respect that decision. Cf. Ysleta Del Sur Pueblo
v. Texas, 596 U.S. 685, 698 (2022) (rejecting interpretation that defied the âusual
presumption that âdifferences in language like this convey differences in meaningââ
(quoting Henson v. Santander Consumer USA, Inc., 582 U.S. 86 (2017))). We do not
doubt that drafters sometimes use different phrases interchangeably, but the
Environmental Groups have not overcome the presumption to contrary.
Finally, the statute does not undercut our reading in the way the Environmental
Groups contend. They say that the CWA provision authorizing the Corps to issue
permits is silent on whether the Corps can narrowly define a projectâs purpose
according to its multiple, underlying goals. 33 U.S.C. § 1344. And, they continue,
28
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 29
our interpretation would thus inject a ânon-statutory factor[]â into the permitting
analysis. Appelleesâ Br. at 34. But that is how regulations like this work; they gloss
the statute. See 33 U.S.C. § 1344(b) (instructing EPA Administrator to develop
regulations to guide the permitting process). Indeed, under the Environmental
Groupsâ argument, we would have to reject all of § 230.10(a)(2)âs considerationsâ
cost, existing technology, or logisticsâbecause none are explicitly stated in the
statute.
We conclude that § 230.10(a)(2) unambiguously allows the Corps to define
overall project purposes with more specific reference to the applicantâs multiple,
related purposes. 11 The Corpsâs definition of the Moffat Projectâs overall project
purposes rested on a sound interpretation of § 230.10(a)(2). That definition was
therefore not arbitrary, capricious, or otherwise contrary to law.
The Environmental Groups next argue that the Corps arbitrarily concluded that
the Moffat Projectâs dual purposes should be incorporated into a single project,
instead of separate projects. But the Environmental Groups overlook the deference
we owe to the Corpsâs determination to address both purposes in a single project.
And the Corps explained why it made sense to address Denver Waterâs goal of
11
The Environmental Groups invoke Auer deference and urge us to defer to
the EPAâs interpretation, which up to January 2026 read âoverall project purposesâ
and âbasic purposeâ interchangeably. But the EPA now interprets § 2310.10(a)(2) to
supply two different meanings to those phrases, just as a plain reading of the text
supports. In any event, Auer deference has no role to play when a regulation is
unambiguous, as § 230.10(a)(2) is. See Kisor v. Wilkie, 588 U.S. 558, 573â74
(2019).
29
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 30
increasing water supply to the Moffat Treatment Plant: âthe multiple needs . . . are
not âindependentâ but rather are interconnected in the water supply issues that Denver
Water is facing. Failing to address any one of the issues would jeopardize Denver
Waterâs ability to meet projected demand needs.â App. 1059. âTherefore, supplying
water to the Moffat Collection System was appropriately used as a criterion for
alternative screening.â App. 1062. That explanation satisfies us that the Corps did
not âentirely fail[] to consider an important aspect of the problem.â Am. Wild Horse
Campaign, 144 F.4th at 1188.
The Environmental Groupsâ final argument fails, too. They suggest the
Corpsâs narrow definition predetermined the alternatives analysis by âdefin[ing] a
project in order to preclude the existence ofâ all practicable alternatives, leaving
Denver Waterâs project as the only viable choice. Appelleesâ Br. at 47 (quoting
Sylvester, 882 F.2d at 409). But the 34 alternatives remaining after the first-step
screening, only ten of which required expanding the Gross Reservoir, tell a different
story. Indeed, the requirement that the proposal deliver water to the Moffat
30
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 31
Treatment Plant eliminated only 19 potential water sources and componentsâout of
303 total. App. 802.
In sum, the Corps did not act arbitrarily or otherwise contrary to law by
screening out proposed alternatives that could not increase water supply to the Moffat
Treatment Plant.
2. Project Cost and Climate Change
Next, the Environmental Groups argue that the Corpsâs analysis of the
alternativesâ costs and climate changeâs effects on feasibility was arbitrary and
capricious. We disagree.
The § 404(b) regulations require the Corpsâs alternatives analysis to consider
the alternativesâ cost and logistics. 12 And because the non-water-dependent
presumption applied to the Moffat Project, the Corps had to clearly demonstrate that
the alternative should be excluded. Still, a reviewing court is deferential to the
Corpsâs analysis. Hillsdale, 702 F.3d at 1156 (explaining that to âclearly
demonstrateâ an alternative should be excluded, the Corps need only take âa hard
look at the proposals and reach[] a meaningful conclusion based on the evidenceâ).
And under NEPA, the Corps was entitled to significant deference. See Seven Cnty.,
605 U.S. at 180. The Environmental Groupsâ CWA and NEPA challenges fail
12
We assume for this appeal that a projectâs âlogisticsâ includes climate
changeâs impact on a projectâs feasibility.
31
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 32
because the record shows the Corps adequately considered cost and climate change
and sufficiently explained its decision.
To estimate a potential alternativeâs total cost, the Corps calculated an
alternativeâs estimated capital costs and then applied a 50% multiplier, which
accounted for contingent costs. Though Denver Water proposed using that cost
methodology, the Corps did not blindly adopt it. The Corps reviewed the
methodology along with a third-party consultant and concluded the methodology
produced âa more representative cost estimate that is suitable for use in comparing
alternatives.â App. 808. To be sure, the consultant explained that this cost
methodology could produce an initial cost estimate very different from the projectâs
final, actual cost, so the results should be used âwith cautionâ and should not form
the basis of a project budget. App. 1352. But even that consultant still concluded
that the methodology produced âa good estimate of the project cost for comparison of
[a]lternatives.â App. 1351 (emphasis added).
Supporting documentation explained why the multiplier should be used and
why it should be 50%. See App. 1269â72, 1364â66. First, exact cost estimatesâ
particularly of contingent costsâwere âimplausibleâ during the EISâs early phases
when the screening procedures were developed âbecause of the lack of detailed
information and project definition.â App. 1364. And that was âparticularly true
when evaluating a wide variety of potentially applicable Project Alternatives for
which a comparable level of detail is not universally available.â App. 1364. Given
the dearth of information needed to make the tailored, particularized cost estimates
32
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 33
urged by the Environmental Groups, the Corps decided to estimate a projectâs cost by
applying a 50% multiplier to the projectâs expected capital costs. It arrived at the
50% number by aggregating the typical percentage cost for discrete componentsâfor
example, 3â5% for land costs and 5â8% for construction management services. App.
1366. These estimates were based on âverification examples and related project
experience.â App. 1351. The supporting documents concluded that the methodology
provided a sound basis to estimate cost for âthe early stages of alternative
development and comparison.â App. 1352.
The Corpsâs explanation for its cost methodology is sufficient to pass
arbitrary-and-capricious muster. See Hillsdale, 702 F.3d at 1178 (âAn agency has
discretion to choose a methodology, so long as it explains why it is reliable.â);
Utahns for Better Transp. v. U.S. Depât of Transp., 305 F.3d 1152, 1166 n.6 (10th
Cir. 2002) (noting that âmore than nothingâ is required for a cost analysis, but not
âan extraordinarily detailed cost estimateâ). To be sure, the record acknowledged
that future information would permit âmore detailed project layouts and
definition[s]â for the proposed alternatives, which would change the estimates. App.
1351. But â[t]here will always be more data that could be gathered; agencies must
have some discretion to decide when to draw the line and move forward with
decisionmaking.â Hillsdale, 702 F.3d at 1169â70 (quoting Habitat Educ. Ctr., Inc. v.
33
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 34
U.S. Forest Serv., 673 F.3d 518, 531 (7th Cir. 2012)). We do not think the Corpsâs
choice of cost methodology was arbitrary or capricious.
The Environmental Groups next argue that the Corps failed to adequately
consider the Moffat Projectâs logistics and clearly demonstrate that the Moffat
Project was âcapable of being done.â 40 C.F.R. § 230.10(a)(2). In their view,
climate change will lead to reduced and earlier peak stream flows, which will in turn
limit the amount of water that Denver Water can deliver to the Moffat Treatment
Plant. Reduced stream flows would limit the amount of water able to be diverted
from the Western Slope; earlier peak stream flows occurring in a condensed
timeframe (rather than being spread out throughout the season) would exceed the
Moffat Tunnelâs capacity, leaving it unable to transport the required amount of water.
The Corps discounted the second point because the Moffat Tunnel is not the
only way the Project would increase water to the Reservoir. App. 847â50. In
response to a public comment on the Final EIS, the Corps explained that 10,000 acre-
feet per year âis brought through the Moffat Tunnel on an average basisâ and â[t]he
remainder of the water would come from the reoperation of Denver Waterâs entire
collection system.â App. 580. The total 18,000 acre-feet per year would still be
âphysically stored inâ the Gross Reservoir, which could then supply the required firm
yield. To show that the 18,000 acre feet of firm yield would be met, the Corps
pointed to âdecades of dataâ and âindependent analysisâ by the Corps. App. 580.
Relatedly, the Corps also rejected using a quantitative model to measure the
reductions of stream flow resulting from climate change. That decision falls within
34
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 35
the Corpsâs discretion. See Natâl Audubon Socây v. U.S. Army Corps of Engârs, 991
F.3d 577, 585 (4th Cir. 2021). The Corps explained that climate change could affect
stream flows in the region, which could in turn impact the amount of water Denver
Water can divert to the Gross Reservoir. App. 949. But whether that possibility
would come to pass was, in the Corpsâs view, speculative: âalthough climate models
show general agreement that temperatures are likely to increase in the west, there is
less agreement about how this change will influence water resources.â App. 950.
Indeed, recent studies on climate changeâs effect on stream flow showed that more
research is needed âbefore estimates on stream flow response to climate change can
be utilized with accuracy and certainty.â App. 951.
And even the Corpsâs statement that comes closest to suggesting that climate
change would decrease firm yield to the Moffat Treatment Plant is couched in a
speculative conditional. App. 949. The Corps said that the Western Water
Assessment (a scientific study from 2008) predicted that water runoff would shift
earlier in the spring, and citing that study, the Corps speculated that â[i]f this were to
occur, it is likely that the yield of the Moffat Collection System would decreaseâ due
to âcapacity constraints.â App. 949. But the Corps observed that even the Water
Assessment itself cautioned that an âassessment and quantification of specific climate
change impacts on water resourcesâ was âbeyond the scope of the[] study.â App.
949. The Corps made a judgment, based on its scientific and technical expertise, that
existing scientific research did not show a clear link between climate change and
decreased firm yield to the Reservoir. The record thus demonstrates that the Corps
35
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 36
considered and meaningfully evaluated whether climate change would decrease the
projectâs near-term firm yield and render the project impracticable. That
determination was not arbitrary or capricious.
The Environmental Groups object that the Corps âignored climate change data
and common sense, refusing to use well-established modelsâ to quantify climate
changeâs impact on stream flows. Appelleesâ Br. at 54â55. But the Corps gave a
reasonable explanation for the modelsâ unreliability. It noted that âhydrological
modeling of the impact of rising temperatures on water resources in mountainous
western regions vary widelyâ and that variability is âhigh in Colorado.â App. 949.
âThis variation is primarily due to the lack of sufficient water-flow data . . . and
difficulty in modeling weather patterns.â App. 949. Accordingly, the Corps
concluded that âthere is no generally-accepted scientific method to correlate air
temperature changes with incremental changes in stream flow or reservoir levels.â
App. 949. The Corps meaningfully evaluated these models and chose not to include
quantitative modeling of climate changeâs effects in its EIS. We owe that reasonable
determination deference. See W. Watershed Project v. U.S. Bureau of Land Mgmt.,
76 F.4th 1286, 1298 (10th Cir. 2023).
Finally, the Environmental Groups cite the Colorado River Water Availability
Study, which they say shows that climate change will reduce firm yield to reservoirs.
But the Corps consideredâand rejectedâthe reliability of that and similar studies,
one of which showed that in the Colorado River Basin, âno consistent trends in
annual precipitation have been detected over the last 100 yearsâ and âclimate models
36
Appellate Case: 25-1137 Document: 161-1 Date Filed: 09/15/2026 Page: 37
do not agree whether annual mean precipitation will increase or decrease in Colorado
by 2050.â App. 581. In the end, the Environmental Groups ask us to substitute our
judgment for the Corpsâs. They point out scientific studies that, in their view, rebut
the Corpsâs reading of the scientific literature and ask us to opine on what the
scientific research establishes. But our job is not to second-guess the Corpsâs
assessment as long as it rests on a reasoned basis.
* * *
In sum, the Corpsâs analyses of cost and climate change deserve deference.
The Corpsâs decisions to use a 50% multiplier and not to quantitatively analyze
climate changeâs effects âhad a rational basis and considered the appropriate factors.â
Hillsdale, 702 F.3d at 1178. The Corps therefore did not act arbitrarily or
capriciously when evaluating the alternativesâ costs and feasibility. 13
III. Conclusion
For the foregoing reasons, we reverse the district court, vacate the permanent
injunction, and remand with instructions to enter judgment against the plaintiff.
13
Because we conclude the Corps did not violate the CWA or NEPA, we do
not reach the issues surrounding the scope of the district courtâs remedy.
37