Back to feedAnalyzed Oct 2, 2026 View on CourtListener
(Siemens waiver upheld)CivilCourt of AppealsAppeal
Alstom Transportation, Inc. v. FRA
- Court
- Court of Appeals for the D.C. Circuit
- Decided
- Sep 25, 2026
- Docket
- 25-5456
- Judges
- Not listed
Detailed analysis & 3-line summary
AI breakdown
Where this case stands
District court: the case for lack of standing.
This decision ¡ Appeal
(Siemens waiver upheld)
TL;DR
- 1Alstom challenged a waiver that let Brightline buy foreign trains instead of U.S.-made ones for a $3 billion project.
- 2The court ruled in favor of the waiver, citing insufficient U.S. production of high-speed trains.
- 3The court decided the waiver was lawful as there were no domestic trains meeting the speed requirements.
Key issues
- 1
Does Alstom have standing to challenge the waiver?
Holding ¡ Yes, Alstom has standing because it showed potential lost profits linked to the waiver.
- 2
Was the 's waiver decision arbitrary or contrary to law?
Holding ¡ No, the waiver was not arbitrary since no domestic trains met the speed requirements at the time.
Why it matters
This decision impacts companies involved in large-scale infrastructure projects and the conditions under which they may source materials internationally.
If you were the judge?
Rail company fights over $3 billion train deal
- 1The government gave $3 billion to help build a fast train line between two big cities.
- 2Brightline wants to buy trains from overseas instead of from Alstom's U.S. factory.
- 3Alstom argues the waiver allowing overseas purchase breaks the rules and hurts its business.
Should the 's waiver for Siemens be thrown out?
Be the first jurorParties
Appellant
Alstom Transportation, Inc.
Appellee
FRA
Roles are inferred from the case caption.
Opinion of the court
United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued April 27, 2026 Decided September 25, 2026
No. 25-5456
ALSTOM TRANSPORTATION, INC.,
APPELLANT
v.
FEDERAL RAILROAD ADMINISTRATION, ET AL.,
APPELLEES
Appeal from the United States District Court
for the District of Columbia
(No. 1:24-cv-02098)
Vincent Levy argued the cause for appellant. With him on
the briefs were Jack Millman, Jessica Marder-Spiro, Daniel
Fahrenthold, and Nicholas H. Hallock.
Gabriel I. Schonfeld, Attorney, U.S. Department of
Justice, argued the cause for federal appellees. With him on
the brief were Brett A. Shumate, Assistant Attorney General,
August Flentje, Attorney, and Charles E. Enloe, Assistant
General Counsel, U.S. Department of Transportation.
Alice E. Loughran argued the cause for intervenor-
appellee DesertXpress Enterprises, LLC. With her on the brief
2
were Eugene E. Stearns, Matthew W. Buttrick, Veronica L. De
Zayas, and Paul Hurst.
Andrew D. Prins argued the cause for intervenor-appellee
Siemens Mobility, Inc. With him on the brief were Nicholas
L. Schlossman, Philip J. Perry, and Lia Rose Barrett.
Before: KATSAS, WALKER, and GARCIA, Circuit Judges.
Opinion for the Court filed by Circuit Judge KATSAS.
Opinion dissenting in part filed by Circuit Judge WALKER.
KATSAS, Circuit Judge: The Federal Railroad
Administration awarded Brightline West $3 billion to support
construction of a high-speed railroad between Southern
California and Las Vegas. The agency waived a statutory
requirement that Brightline buy only goods produced in the
United States. Brightline then chose to buy trains
manufactured abroad by Siemens Mobility, Inc., rather than
trains manufactured domestically by Alstom Transportation,
Inc. Alstom now challenges the waiver. We hold that Alstom
has standing to do so, but its claims fail on the merits.
I
The Infrastructure Investment and Jobs Act authorizes the
Secretary of Transportation to award grants to support intercity
passenger railroads. 49 U.S.C. § 24911. The Secretary has
delegated responsibility for administering this program to the
Federal Railroad Administration (FRA). 49 C.F.R. § 1.89(a).
The Act subjects grants to the âBuy Americaâ requirement
set forth in section 22905 of title 49. See 49 U.S.C. § 24911(i).
That provision permits federal funding of a project âonly if the
steel, iron, and manufactured goods used in the project are
3
produced in the United States.â Id. § 22905(a)(1). However,
the FRA may waive this requirement if it concludes that âthe
steel, iron, and goods produced in the United States are not
produced in a sufficient and reasonably available amount or are
not of a satisfactory qualityâ for use in the project. Id.
§ 22905(a)(2)(B).
II
The Nevada Department of Transportation has engaged
Brightline West, a privately owned railroad company, to build
a high-speed passenger rail connection between Rancho
Cucamonga, California, and Las Vegas, Nevada. In 2023, the
Department and Brightline sought federal funding for this
project under the Infrastructure Investment and Jobs Act. They
estimated the total cost of this project at $12 billion. On
December 8, 2023, the FRA awarded some $3 billion in federal
funding to the project.
Brightline sought bids for ten trains capable of traveling at
speeds exceeding 186 miles per hour. Only two companies
submitted bids: Siemens Mobility, Inc., and Alstom
Transportation, Inc. Siemens proposed to supply Brightline
with its Velaro Novo trains, which travel in Europe at speeds
of up to 220 miles per hour. Siemens proposed to build the first
two trains at its headquarters in Germany, while training
American workers in the process, and then to build the other
eight trains at a new factory to be constructed in the United
States. Alstom proposed to supply Brightline with ten trains
built in the United States, using technology developed for its
Avelia Liberty trains. Those trains have been selected for use
in the Northeast Corridor under the Acela brand and presently
have a maximum speed of 160 miles per hour. Apart from the
trains themselves, both Siemens and Alstom proposed to build
4
abroad certain train components that no company produces
domestically.
After approving federal funding, the FRA proposed to
waive the Buy America requirements for both Siemens and
Alstom. Notice of Proposed Nonavailability Waiver of Buy
America Requirements, 88 Fed. Reg. 89,015 (Dec. 26, 2023).
Because Brightline had not yet selected its preferred vendor for
the trains, the agency planned to grant Brightline a waiver for
either Siemensâs or Alstomâs proposal. Id. at 89,016â17. In
the agencyâs tentative judgment, a waiver would be justified
because the high-speed trains demanded by Brightline are not
produced in the United States. See id.
The FRA reached a final decision on May 24, 2024.
Notice of Nonavailability Waiver of Buy America
Requirements, 89 Fed. Reg. 45,934 (May 24, 2024). By that
time, Brightline had selected Siemens as its âpreferredâ vendor,
so the FRA finalized the waiver only as to Siemens. Id. at
45,934; see J.A. 73 (notice from Brightline to FRA). In doing
so, the agency found that âthere are currently no domestic
manufacturers of high-speed trainsetsâ able to travel at the
speeds demanded by Brightline. 89 Fed. Reg. at 45,936.1
One week after the waiver decision, Brightline contracted
to buy the trains from Siemens. See Limited Remarketing
Memorandum, Brightline West Passenger Rail Project
Revenue Bonds Series 2020A-4, at 13 (July 25, 2024),
available at bit.ly/40jiBg8 (âOn May 31, 2024, the Company
entered into a rolling stock purchase agreement with Siemens
1
In its decision, the FRA stated that âhigh-speed trainsetsâ are
those that can travel âin excess of 125 mph.â 89 Fed. Reg. at 45,936.
The agency now describes that figure as a scrivenerâs error, and no
party disputes this characterization. In fact, Brightline had
demanded trains that could travel over 186 miles per hour.
5
to supply trainsets for the Project, after a multi-year global
qualification process.â).
About six weeks later, Alstom sued to challenge the
waiver under the Administrative Procedure Act. J.A. 14
(complaint). Brightline and Siemens intervened in support of
the FRA, and all parties moved for summary judgment. The
district court dismissed the complaint on the ground that
Alstom lacked Article III standing. Alstom Transp., Inc. v.
FRA, No. 24-cv-02098, 2025 WL 3640503 (D.D.C. Dec. 16,
2025). Alstom appealed.
III
A
Article III of the Constitution limits the federal courts to
resolving âCasesâ or âControversies.â U.S. Const. Art. III, § 2.
The case-or-controversy requirement is embodied in the
doctrine of standing, which requires the plaintiff to show that
it has suffered an injury that was caused by the defendant and
likely would be redressed by a favorable judicial decision.
Lujan v. Defs. of Wildlife, 504 U.S. 555, 560â61 (1992).
When a plaintiff seeks to challenge an agencyâs grant of a
benefit to a third party, âstanding is not precluded, but it is
ordinarily substantially more difficult to establish.â Defs. of
Wildlife, 504 U.S. at 562 (cleaned up). In that circumstance,
causation and redressability depend on the behavior of parties
other than the plaintiff or the agency. To establish standing in
such a case, the plaintiff must show two distinct causal chains
connecting the challenged agency action to the plaintiffâs
injury. First, it must show that granting the benefit caused the
third party to harm the plaintiff. Diamond Alt. Energy, LLC v.
EPA, 606 U.S. 100, 112 (2025). Second, it must show that a
favorable judicial decision setting aside the benefit would
6
cause the third party to redress that harm. Id. Predictable
causal chains establishing these elements can support standing,
while speculative ones cannot. Id. In distinguishing
predictable from speculative chains, âall we requireâ is a
âsubstantial likelihoodâ that the plaintiffâs injury is traceable to
the agency action under review and would be redressed by a
favorable decision setting it aside. Competitive Enter. Inst. v.
FCC, 970 F.3d 372, 384 (D.C. Cir. 2020) (CEI).
Each element of standing âmust be supported in the same
way as any other matter on which the plaintiff bears the burden
of proof, i.e., with the manner and degree of evidence required
at the successive stages of the litigation.â Defs. of Wildlife, 504
U.S. at 561. Here, the parties cross-moved for summary
judgment on an administrative record including agency
findings of fact. In this procedural posture, Alstom had to
prove its standing, not merely allege it. Viasat, Inc. v. FCC, 47
F.4th 769, 781 (D.C. Cir. 2022).
âIn considering the likely reaction of third parties, we may
consider a variety of evidence, including the agencyâs own
factfinding, affidavits submitted by the parties, evidence in the
administrative record, arguments firmly rooted in the basic
laws of economics, and conclusions in other agency orders and
rulemakings.â CEI, 970 F.3d at 382 (cleaned up). In particular,
the standing analysis may recognize âcommonsense economic
realitiesâ and draw âcommonsense inferencesâ about how
businesses are likely to respond to them. Diamond Alt. Energy,
606 U.S. at 116.
B
To establish its standing in this case, Alstom asserted three
distinct theories of injuryâlost profits, harm as a competitor,
and procedural injury. We hold that the first theory suffices to
establish its standing, so we do not address the other two.
7
Alstom contends that it lost profits from the waiver that the
FRA granted for Siemens. Without that waiver, Alstom argues,
Brightline likely would have bought trains from it rather than
choose Siemens and thereby sacrifice $3 billion in federal
funding. Moreover, setting aside the waiver would likely
redress its injury for essentially the same reason: Brightline
likely would shift its business from Siemens to Alstom rather
than lose $3 billion in federal funding.
Alstom easily satisfies the requirement to show a concrete
injury. When Brightline awarded the contract to Siemens,
Alstom lost a valuable business opportunity and thus suffered
a pocketbook injury, which is âa prototypical form of injury in
fact.â Collins v. Yellen, 594 U.S. 220, 243 (2021).
As for traceability, Alstom has shown a substantial
likelihood that the FRAâs grant of a waiver for Siemens caused
Brightline to select Siemens, rather than Alstom, to build the
trains at issue. This conclusion seems to us apparent from the
sheer size of the $3 billion federal grant. Absent the waiver,
Brightline could not have chosen Siemens trains for the project
without losing this funding. See 49 U.S.C. § 24911(i). Indeed,
had Brightline agreed to purchase even one train from abroad
without the waiver, it would have lost the entire $3 billion.
Under the Infrastructure Investment and Jobs Act, the FRA
may obligate funds for a project âonly if the steel, iron, and
manufactured goods used in the project are produced in the
United States.â Id. § 22905(a)(1). This means that ânone of
the funds made availableâ by the FRA may be obligated unless
âall ofâ the steel, iron, and manufactured goods used in the
project are produced in the United States. Pub. L. No. 117-58,
div. G, tit. IX, § 70914, 135 Stat. 429, 1298 (2021). The
procedural history of this case confirms the obvious economic
reality that federal funding conditions would drive Brightlineâs
decision: Before selecting Siemens over Alstom to build the
8
trains, Brightline sought a waiver for each of the two bidders.
See 88 Fed. Reg. at 89,017. And although Brightline did
identify Siemens as its âpreferred bidderâ before receiving the
waiver, J.A. 73, it made no contractual commitment to Siemens
until after the FRA had granted the waiver.
We reach the same conclusion as to redressability. This
should not be entirely surprising, as the two causation elements
of standing are âusually flip sides of the same coin.â Diamond
Alt. Energy, 606 U.S. at 111 (cleaned up). The same basic
economic reality showing that the waiver likely caused
Brightline to select Siemens over Alstom on the front end also
shows that, if the waiver were set aside, Brightline would likely
shift its business from Siemens to Alstom rather than lose $3
billion in federal funding.
Resisting this conclusion, the FRA relies chiefly on this
Courtâs decision in Hecate Energy LLC v. FERC, 126 F.4th
660 (D.C. Cir. 2025). In that case, the Federal Energy
Regulatory Commission approved a third partyâs proposal to
grant expedited review of certain transmission upgrades
projected to cost $5 million or less. Id. at 662. A company that
had been denied expedited approval of its more expensive
proposed upgrade challenged the approval for the less
expensive upgrade. Id. at 665. The company argued that
vacating FERCâs approval of the third partyâs proposal would
increase the prospects for quick approval of the more expensive
upgrade. Id. Rejecting that theory of redressability, we
reasoned that our prospective decision would not remove the
third partyâs âincentive or abilityâ to resist expedited approval
of the more expensive project. Id. at 669. No such difficulty
is present here, because vacating the waiver for Siemens would
significantly alter Brightlineâs incentive to buy trains from
Siemens rather than Alstom.
9
The appellees also remind us that âredressability on the
back endâ might diverge from âtraceability on the front endâ if
a ânew status quoâ is âheld in place by other forces besides the
government action at issue.â CEI, 970 F.3d at 385 (cleaned
up). And they claim that things changed when, after the FRA
granted the waiver, Brightline awarded the contract to Siemens.
Perhaps that means Brightline would need to pay Siemens
some money, in the form of a breakup fee or damages, to walk
away from their deal. But the contract appears in neither the
administrative nor the district-court record, and neither
Brightline nor Siemens has told us anything about its terms.
Had the contract posed any serious questions as to
redressability, we suspect that one of those two intervenors
would have put it in the record. Moreover, we have strong
reason to doubt that the contract itself would cement the
commercial arrangement between Brightline and Siemens.
Brightline has projected the cost of all trains for the project to
be $750 millionâa fraction of the $3 billion in federal funding
that Brightline would lose if we set aside the waiver and
Brightline nonetheless maintained its contract with Siemens.
So the prospect of some contractual liability to Siemens would
not likely drive Brightlineâs future purchasing decision.
Beyond formation of the contract, the appellees also
speculate that facts on the ground have changed during the time
this litigation has been pending. The FRA notes that Brightline
has already invested two years and millions of dollars in its
relationship with Siemens. Likewise, Brightline stresses that it
would be loath to proceed with Alstom at this late date. But
Brightline originally sought a waiver for Alstom as well as for
Siemens, and it has conspicuously declined to file an affidavit
swearing off any possibility of working with Alstom in the
future, should that become necessary to preserve its federal
funding. For standing purposes, we consider only the facts as
they stood when this lawsuit was filed in July 2024. See
10
Friends of the Earth, Inc. v. Laidlaw Envât Servs. (TOC), Inc.,
528 U.S. 167, 191â92 (2000). Any later developments
impairing our ability to provide relief to Alstom would bear on
mootness, which the FRA would have to prove. See West
Virginia v. EPA, 597 U.S. 697, 719 (2022). The FRA does not
raise any mootness argument. And even if it did, vague
references to working relationships and performance under an
existing contract, in the shadow of $3 billion in federal funding,
fall short of satisfying its burden to prove mootness.
In sum, our setting aside the waiver would put Brightline
to a stark choice: Shift business from Siemens to Alstom or
else lose $3 billion in federal funding. Commonsense
economic inferencesâindeed obvious onesâmake it
substantially likely that Brightline would shift its business to
Alstom if put to that choice. We therefore conclude that
Alstomâs lost-profits injury is redressable, and Alstom thus has
Article III standing.2
2
The dissent posits that Brightline might avoid this dilemma
by renegotiating its contract with Siemens to provide for exclusively
domestic manufacturing or by seeking a public-interest waiver to the
Buy America requirement. Post, at 6. Neither possibility strikes us
as likely. After a years-long procurement process stretching back to
2019, Siemens made its âbest and finalâ offer in 2024. J.A. 133. The
details are under seal, but suffice it to say that Siemens did not think
it could safely or reliably build the first two trains in the United States
without first having prospective American workers learn the expert
manufacturing, assembly, inspection, and testing processes at its
established manufacturing facility in Germany. Moreover, despite
the stakes involved in locking down a $12 billion project, Brightline
never even raised the possibility of a public-interest waiver under 49
U.S.C. § 22905(a)(2)(A). And if this Court were to hold that a
domestic-unavailability waiver under section 22905(a)(2)(B) is
unavailable, the dissent does not say what other considerations might
support the posited public-interest waiver.
11
IV
Because the district court erred in dismissing this case on
jurisdictional grounds, we must consider whether to remand or
to resolve the merits. Although we ordinarily remand for the
district court to consider the merits in the first instance, we have
discretion to do so ourselves. Mendoza v. Perez, 754 F.3d
1002, 1020 (D.C. Cir. 2014). Factors bearing on our exercise
of this discretion include whether (1) the parties have briefed
the merits here, (2) they have requested a merits decision, (3)
the merits involve purely legal questions, (4) an appeal from
any district-court decision is likely, and (5) the merits are clear.
See id.; Natâl Council for Adoption v. Blinken, 4 F.4th 106,
113â14 (D.C. Cir. 2021).
These considerations support our reaching the merits.
First, the parties fully briefed the merits in this Court. Second,
Alstom has asked us to decide the merits, and neither the FRA
nor Siemens objects. Brightline requests a remand, but that
consideration is not dispositive. See Mendoza, 754 F.3d at
1020. Third, Alstomâs claims raise purely legal issues that we
would consider de novo, with or without a district-court
decision. Fourth, an appeal from any merits decision appears
likely, given the financial stakes of this case. Fifth, the merits
seem to us relatively straightforward, as explained below. And
we add one final consideration: Two years into this $12 billion
infrastructure project, it is better for everyone to know sooner,
rather than later, the basic rules governing the $3 billion in
federal funding.
In declining to reach the merits after reversing a
jurisdictional dismissal, some courts have invoked the rule that
an appellee may not enlarge a judgment in its favor without
taking a cross-appeal. See In re Breland, 989 F.3d 919, 922â
23 (11th Cir. 2021); Remijas v. Neiman Marcus Grp., LLC, 794
12
F.3d 688, 697 (7th Cir. 2015). Here, however, it is the
appellantâAlstomâurging us to render a favorable merits
judgment. Because the cross-appeal rule âis both informed by,
and illustrative of, the party presentation principle,â Greenlaw
v. United States, 554 U.S. 237, 244 (2008), and protects
âinstitutional interests in fair notice and repose,â El Paso Nat.
Gas Co. v. Neztsosie, 526 U.S. 473, 480 (1999), it applies only
when an appellee tries to surprise the appellant by attacking the
judgment for the first time in its response brief. Thus, in an
early case expounding the cross-appeal rule, Justice Story
explained that an appellee âwill be deemed to have waivedâ
any attacks on a judgment that it did not cross appeal. Canter
v. Am. Ins. Co., 28 U.S. (3 Pet.) 307, 318â19 (1830). That
concern is absent when the appellant seeks to convert a
jurisdictional dismissal into a merits decision.
In any event, even if the cross-appeal rule did
presumptively apply here, we have described it as a non-
jurisdictional rule subject to judge-made exceptions. Shatsky
v. PLO, 955 F.3d 1016, 1030 (D.C. Cir. 2020). Here, an
exception would be warranted for the reasons ticked off above,
including the desire to avoid extended uncertainty over the
rules for a multi-billion-dollar infrastructure project. See Ream
v. U.S. Depât of Treasury, 174 F.4th 480, 486 (6th Cir. 2026).
V
On the merits, Alstom argues that the waiver is both
contrary to law and arbitrary. We review legal questions
regarding the scope of the waiver provision de novo, without
deference to the district court or the agency. See Loper Bright
Enters. v. Raimondo, 603 U.S. 369, 394 (2024). To survive
judicial review for arbitrariness, the waiver decision need only
be reasonable and reasonably explained. See 5 U.S.C.
13
§ 706(2)(A); FCC v. Prometheus Radio Project, 592 U.S. 414,
423 (2021).
A
The Infrastructure Investment and Jobs Act permits
funding for Brightlineâs project âonly if the steel, iron, and
manufactured goods used in the project are produced in the
United States.â 49 U.S.C. § 22905(a)(1). But the FRA may
waive this requirement if it finds that âthe steel, iron, and goods
produced in the United States are not produced in a sufficient
and reasonably available amount or are not of a satisfactory
qualityâ for use in the project. Id. § 22905(a)(2)(B). The FRA
granted a waiver permitting Brightline to buy two trains
manufactured abroad after finding that âthere are currently no
domestic manufacturers of high-speed trainsetsâ able to travel
at the speeds demanded by Brightline. 89 Fed. Reg. at 45,936.
Alstom does not challenge this factual finding as unsupported
by substantial evidence or otherwise arbitrary. On the contrary,
Alstom has expressly disclaimed any such challenge. Reply in
Supp. of Pl.âs Mot. for Prelim. Inj. at 12 n.19, Alstom Transp.,
Inc. v. FRA, No. 1:24-cv-02098 (D.D.C. filed Dec. 4, 2024),
ECF Doc. 64 (âAlstom has never disputed the FRAâs
conclusion that no manufacturer in the U.S. was yet producing
trains operating above 186 miles per hourâ).
Instead, Alstom contends that the availability of the waiver
provision depends on future production of the relevant goods.
When the FRA considers whether the relevant goods âare not
producedâ in the United States in sufficient quantity or
satisfactory quality, 49 U.S.C. § 22905(a)(2)(B), Alstom
would compel the agency to consider whether such goods will
be produced in the future. But verb tense matters in statutory
construction. See United States v. Wilson, 503 U.S. 329, 333
(1992). And in the waiver provision, Congress chose the
14
present tense to frame a question whether the relevant goods
âareâ produced domestically at the time of the waiver decision.
In arguing to the contrary, Alstom cites no textual features
of the waiver provision itself. Instead, Alstom invokes the
underlying Buy America requirement, which provides that the
FRA âmay obligateâ federal funds for a project only if the
âgoods used in the project are producedâ in the United States.
49 U.S.C. § 22905(a)(1). Alstom posits that the phrase âare
produced,â as used in this requirement, refers to goods that will
be produced in the future. Then, Alstom invokes the
presumption of consistent usage to contend that, if the phrase
âare producedâ in the requirement refers to some future time,
then so too must the phrase âare ⌠producedâ in the waiver
provision.
This argument is clever but ultimately unpersuasive. As a
general matter, courts presume that a statutory term âbears a
consistent meaning throughoutâ the statute. USPS v. Konan,
607 U.S. 391, 403 (2026). But this presumption âis particularly
defeasible by context.â A. Scalia & B. Garner, Reading Law:
The Interpretation of Legal Texts 171 (2012); see Atl. Cleaners
& Dyers, Inc. v. United States, 286 U.S. 427, 433 (1932) (âIt is
not unusual for the same word to be used with different
meanings in the same act.â). And we are skeptical that the
presumption carries weight in determining the temporal scope
of a participle like âproduced,â which is often ambiguous as a
matter of basic grammar. Participles may be used as part of a
verb phrase carrying a tense or may be used as an adjectival
passive. See R. Huddleston & G. Pullum, The Cambridge
Grammar of the English Language 78â79, 1436â39 (2002). In
the latter case, the adjective is âtenselessâ and may refer to past,
present, or future events. Bernal v. NRA Grp., LLC, 930 F.3d
891, 895 (7th Cir. 2019) (quoting Huddleston & Pullum, supra,
at 162); see also TQP Dev., LLC v. Intuit Inc., No. 2:12-cv-180,
15
2014 WL 2810016, at *1 (E.D. Tex. June 20, 2014) (Bryson,
J., sitting by designation). In that instance, other parts of the
sentence must determine the temporal scope of the participle.
See Bernal, 930 F.3d at 895 (âEverything depends on the
context.â).
We agree with Alstom that the phrase âare produced,â as
used in the Buy America requirement, refers to future
production. Again, that requirement provides that the FRA
âmay obligateâ federal funds only if the âgoods used in the
project are produced in the United States.â 49 U.S.C.
§ 22905(a)(1). In this provision, the participial phrase
âproduced in the United Statesâ plainly functions as an
adjective modifying the noun âgoods.â Replace the participial
phrase with a synonymous, true adjectiveâsay âdomesticââ
and the requirement retains its sense and coherence: The FRA
may fund a project only if the âgoods used in the project are
domestic.â Or replace the participial phrase with a
synonymous prepositional phrase (which can function
adjectivally but not as a verb): The FRA may fund a project
only if the âgoods used in the project are of United States
origin.â Again, the requirement retains its sense and
coherence. Moreover, context makes clear that the participial
phrase refers to goods produced in the future, for the Buy
America requirement contemplates a sequence of events that
begins with an FRA funding decision, to be followed by
production and then use of the relevant goods in the future.
This case illustrates that point; not surprisingly, Brightline
sought federal funding of the high-speed trains for its project
before the trains were either âproducedâ or âused.â 88 Fed.
Reg. at 89,015; J.A. 131.
The waiver provision has a different grammatical
structure. It applies if the âgoods produced in the United States
are not produced in a sufficient and reasonably available
16
amount or are not of a satisfactory quality.â 49 U.S.C.
§ 22905(a)(2)(B). In that provision, the second participle
âproducedâ is not used tenselessly and adjectivally to modify
the noun âgoods.â Substitute a true adjective for the participle,
and the sentence becomes garbled: Nobody would craft a
waiver provision keyed to whether the relevant goods âare not
domestic in a sufficient and reasonably available amount or are
not of a satisfactory quality.â Instead, âproducedâ is used as
part of a verbal passiveâa âdynamic verb phrase that describes
the actâ of physically producing the goods. TQP Dev., 2014
WL 2810016, at *2. And as explained above, this verb carries
with it the present tense. So, nothing about the Buy America
requirement supports an atextual reading of âare ⌠producedâ
in the waiver provision to mean âwill be ⌠produced.â In the
provisions at issue, different grammatical structures indicate
different temporal frames of reference.
In short, the FRA correctly concluded that the waiver
provision applied based on its uncontested finding that no
domestic manufacturer, at the time of the waiver, was
producing the kind of high-speed trains that Brightline
demanded.
Alternatively, Alstom contends that the FRA defined the
relevant âgoodsâ too narrowly. Alstom urges that high-speed
trains cannot be different goods just because their technologies
differ. Otherwise, Alstom says, Brightline could obtain a
waiver for Velaro Novo trains manufactured in Germany just
because their technology differs slightly from the Avelia
Liberty trains manufactured domestically. We agree with
Alstomâs premise that, at some point, distinguishing goods
based on immaterial technological or other differences might
be arbitrary, but we do not read the FRAâs decision to rest on
such immaterial differences. As explained above, the agency
rested its waiver on a finding that âthere are currently no
17
domestic manufacturers of high-speed trainsetsâ capable of
traveling at the 186 miles per hour demanded by Brightline. 89
Fed. Reg. at 45,936. Alstom neither challenges that finding nor
directly contends that the FRA, in assessing domestic
availability, arbitrarily excluded trains capable of traveling at
almost that speed. The passages in the FRAâs analysis
highlighted by Alstom, where the agency stressed the
technological differences between the Velaro Novo and Avelia
Liberty trains, simply underscore that basic point.
B
Alstom argues that the waiver, even if not contrary to law,
was nonetheless arbitrary. Alstom contends that the FRA did
not reasonably explain its decision to issue the discretionary
waiver. We disagree. As noted above, the FRA did highlight
the significant technological differencesâresulting in
significant speed differencesâbetween the two trains. 89 Fed.
Reg. at 45,937. Moreover, the FRA explained that â[h]igh
speed rail trainsets are highly specialized and require highly
skilled labor and specific equipment, manufacturing, testing,
and commissioning facilities to ensure safe and efficient
operations.â Id. So, the agency could reasonably allow
Brightline to work with a company that has already produced
trains proven to travel safely at such high speeds, rather than
hope a different company would manage to upgrade its existing
technology to support substantially increased speed. Finally,
the FRA stressed that the waiver, limited to two trains and
certain components that all agreed were not domestically
available, was ânarrowly tailored and limitedâ as much as
reasonably possible. Id. at 45,938. That was more than enough
to avoid arbitrary decision-making.
18
VI
For these reasons, we agree with the district court that
Alstom is entitled to no relief. We convert the district courtâs
jurisdictional judgment into a merits-based judgment, see
Fernandez v. Centerplate/NSBE, 441 F.3d 1006, 1009â10
(D.C. Cir. 2006) (per curiam), which we affirm as so modified.
So ordered.
WALKER, Circuit Judge, dissenting in part:
Brightline West is building a high-speed rail system.
Alstom Transportation wants to sell trains to Brightline. But
Brightline instead chose to buy trains from Siemens Mobility.
An action by the Federal Railroad Administration made
Brightlineâs choice easier. Alstom has sued to vacate that
agency action. It thinks that Brightline will then choose to buy
trains from Alstom.
That chain of events is possible. But Alstom has not
shown that it is sufficiently predictable. So Alstom does not
have standing to sue.
I. Brightline Prefers Siemensâ (Proven) Trains to Alstomâs
(Unproven) Trains
Brightline is building a high-speed rail connecting Las
Vegas with southern California.1 The trains will reach speeds
of at least 186 miles per hour.2 To support the project, the
Federal Railroad Administration provided $3 billion.3
Siemens bid to build the trains that Brightline needs.4 So
did Alstom.5
But Alstom had a problem. At that time, its American
facilities were not making trains âservice proven at speeds in
1
The Nevada Department of Transportation partnered with
Brightline, a privately owned railroad, to develop the project. See
JA 31. Throughout this opinion, I refer to decisions on behalf of their
partnership as Brightlineâs decisions.
2
See JA 129.
3
See JA 129â32.
4
See JA 242.
5
See id.
2
excess of 125 mph.â6 So Alstom proposed a train it had never
before built â a new version of its âAveliaâ train modified to
go 186 mph.7
In contrast, Siemens proposed its âVelaro NOVO.â8 That
high-speed train was already operating in Europe.9 And it was
already capable of going 186 mph.10
Brightlineâs federal funding requires it to buy American-
made trains unless it receives a Buy America waiver from the
FRA.11 Alstom and Siemens each proposed to use foreign-
made train car shells.12 So Brightline sought a ânonavailability
waiverâ broad enough to accommodate either Siemensâ or
Alstomâs proposal.13
Before the FRA made a final decision about the requested
waiver, Brightline chose not to contract with Alstom.14
Instead, Brightline selected Siemens â the company
proposing to build trains already proven to be fast enough for
Brightlineâs project.15 After announcing that selection,
6
JA 41.
7
JA 41â42, 74.
8
JA 41â42.
9
See JA 32, 239.
10
JA 78, 242.
11
See 49 U.S.C. § 22905.
12
See JA 32.
13
See JA 32â33; 49 U.S.C. § 22905(a)(2)(B).
14
JA 239, 244. Cf. SEINFELD: The Lip Reader (NBC television
broadcast, aired Oct. 28, 1993) (Gwen: âItâs not you. Itâs me.â
George: âYouâre giving me the âitâs not you, itâs meâ routine? I
invented âitâs not you, itâs me.â Nobody tells me âitâs them not me.â
If itâs anybody, itâs me!â Gwen: âAll right. George, itâs you.â).
15
JA 73.
3
Brightline requested and received a final Buy America waiver
allowing Siemens to build its first two trains in Germany, with
American workers there to learn the manufacturing process
before production of the remaining eight trains shifted to a new
facility in Nevada.16
II. Alstom Lacks Standing
To sue, a plaintiff must have standing. Standing requires
an injury caused by the defendant and redressable by the
court.17 Because the court cannot redress Alstomâs injury,
Alstom lacks standing.
A. Alstom Cannot Satisfy Its Burden with Guesswork
When (as here) a plaintiff challenges government action
directed toward third parties rather than toward the plaintiff,
redressability âoften depend[s] on how regulated third parties
not before the court will act in response to the . . . judicial
reliefâ requested.18 That requires courts to distinguish the
requested reliefâs âpredictableâ effects on third parties from its
âspeculative effects.â19
For that inquiry, courts must not blind themselves to
âcommonsense economic inferences.â20 If those inferences
16
JA 39, 73, 242â43.
Brightline announced its selection of Siemens on May 1, 2024. JA
73. The FRA granted the final waiver on May 24. JA 39. Brightline
and Siemens consummated the final agreement on May 31. JA 250.
17
Lujan v. Defenders of Wildlife, 504 U.S. 555, 560â61 (1992).
18
Diamond Alternative Energy, LLC v. EPA, 145 S. Ct. 2121, 2134
(2025).
19
Id. (cleaned up).
20
Id. at 2138.
4
make a favorable outcome for the plaintiff âsufficiently
predictable,â they can support redressability.21 For instance, it
is âpredictableâ â if not certain â that invalidating
regulations requiring automakers to make fewer gas-powered
vehicles will result in more sales of gas.22 That is at least so
when the inference is supported by record evidence.23
But plaintiffs cannot rely on âguesswork as to how
independent decisionmakers will exercise their judgment.â24
They must instead show that the independent decisionmakers
âwill likely react in predictable ways.â25 So when a
disappointed bidder challenges government action that has
eliminated a regulatory obstacle to the winning bidderâs
contract with a third party, the disappointed bidder must show
that the third-party would likely respond to the vacatur in a way
that redresses the disappointed bidderâs injury. Sometimes
âcommonsense economic inferencesâ will make that response
âsufficiently predictable,â but sometimes those inferences will
make that response unlikely.26 In other words, sometimes
economic inferences will support the causal chain asserted by
the plaintiffs, and sometimes they will undermine it.
In todayâs case, Alstom must do more than show that one
imaginable sequence of events begins with vacatur of the
waiver, is followed by Brightline abandoning its relationship
with Siemens, and ends with Brightline selecting Alstom. The
21
Id. (cleaned up).
22
Id. at 2141.
23
See id. at 2138 n.5.
24
Murthy v. Missouri, 144 S. Ct. 1972, 1986 (2024) (quoting Clapper
v. Amnesty International USA, 568 U.S. 398, 413 (2013)).
25
Id. (quoting Department of Commerce v. New York, 139 S. Ct.
2551, 2566 (2019)).
26
Diamond Alternative Energy, 145 S. Ct. at 2138 (cleaned up).
5
question is instead whether âcommonsense economic
inferencesâ and Alstomâs evidence make that sequence
âsufficiently predictable.â27 If so, Alstomâs economic injury is
redressable. If not, Alstom lacks standing.
B. Alstom Has Not Demonstrated Redressability Because
a Brightline-Alstom Relationship Is Not âSufficiently
Predictableâ
Alstom says it is âsufficiently predictableâ that vacatur of
the waiver will result in Brightline buying trains from Alstom
because vacatur will impose a binary choice on Brightline.28
Option One â keep Siemens, and lose $3 billion in federal
funding. Option Two â dump Siemens, switch to Alstom, and
retain the $3 billion in federal funding.29 And that, according
to Alstom, is an offer that Brightline canât refuse.30
If those were Brightlineâs only two options, I might agree
with Alstom. After all, though Brightline prefers Siemensâ
(proven) trains to Alstomâs (unproven) trains, the benefit of
three billion federal dollars probably outweighs the risks
associated with selecting the unproven Alstom. Similarly, Iâd
prefer a first-row seat behind home plate at Wrigley Field to a
seat in the outfield bleachers, but not if you paid me $3 billion
to sit with the Bleacher Bums.
The problem for Alstom is that the record provides little
reason to assume that Brightline will face the binary choice that
Alstom imagines. Rather, even after vacatur, Brightline might
27
Id. (cleaned up).
28
Id. (cleaned up).
29
See Appellant Reply Br. 14â15.
30
See Appellant Br. 34.
6
well be able to salvage its relationship with Siemens and keep
the $3 billion. For example:
⢠Brightline and Siemens might attempt to renegotiate the
manufacturing plan so that all ten trains are built
domestically, rather than two in Germany and eight in
the United States;
⢠Brightline might reduce the order to eight American-
made trains; or
⢠Brightline might seek a Buy America waiver on a
different statutory ground, such as a waiver based on
the public interest, rather than the challenged waiver
based on nonavailability.31
To be clear, itâs not certain which, if any, of those options
Brightline would explore if the FRAâs waiver is vacated.
Perhaps Brightline actually would abandon a contractual
partner it âspent more than five years pickingâ in favor of a
suitor it previously rejected before it received the FRAâs
waiver.32 I cannot be sure. But that uncertainty is Alstomâs
problem because the burden is Alstomâs.
Alstom has not satisfied that burden. It has not established
that its predicted chain of events â Brightline breaching its
contract with Siemens and choosing Alstom in its place â is
sufficiently likely in light of Brightlineâs other possible paths.33
31
See Oral Arg. Tr. 18â19 (other options available); 49 U.S.C.
§ 22905(a)(2)(A) (public-interest waiver).
32
Oral Arg. Tr. 19.
33
Alstom notes that âno party present[s] any evidence to supportâ
the notion that Brightline might re-negotiate with Siemens.
Appellant Br. 36. But where both options follow from âpredictable,
commonsense inferences,â Diamond Alternative Energy, 145 S. Ct.
7
In fact, there are three interrelated facts that make a Brightline-
Alstom relationship pretty far-fetched.
First, before Brightline selected Siemens, Siemens had
already built and introduced into service the train it proposed
for Brightline â a train capable of meeting Brightlineâs
requirements.34 By contrast, Alstom had not.35
Second, before the FRA definitively approved the waiver
for Siemensâ proposal, Brightline selected Siemens.36 So even
though Brightline and Siemens wanted the first two trains to be
built in Germany, it appears that their relationship did not
depend on it. And for good reason â again, unlike Alstom,
Siemens had already proven it could build the train that
Brightline wanted.
Third, before Alstom sued, Brightline and Siemens had
already formed a contract.37 And Siemens might, by then, have
begun to perform on it.38 Either way, âcommonsense economic
inferencesâ39 would suggest that a company in Brightlineâs
position might be loath to abandon a âkeystone supplier
at 2136, Alstom bears the burden of showing that Brightline is more
likely to jump off the Siemens train and hop on the Alstom train.
34
See JA 41, 241â43.
35
See JA 23, 32, 48; Oral Arg. Tr. 32 (âAll we have in the record . . .
is that they would have to make substantial modifications to increase
power capacity and traction to achieve the required speed and
performance capacity for the project. . . . [A]nd they had never
manufactured in their New York facilities any type of trainsets that
could meet this requirement.â).
36
See JA 24, 241â44.
37
See JA 133, 250.
38
See JA 133.
39
Diamond Alternative Energy, 145 S. Ct. at 2138.
8
relationshipâ consummated by a contract and integral to âone
of the largest infrastructure projects in the nation.â40
III. Conclusion
In its attempt to show that vacatur of Brightlineâs waiver
will redress Alstomâs economic injury, Alstom says Brightline
will choose billions in federal funding over Alstomâs
competitor, Siemens.
But that is a false dichotomy.
Brightline might instead stick with Siemens and keep the
federal funding â perhaps by making Siemens build all ten
trains domestically, perhaps by purchasing only the eight trains
Siemens already planned to build domestically, or perhaps by
obtaining a public-interest waiver allowing Siemens to stick
with its original plan.
Because Brightline is unlikely to swap the supplier it
already chose for the supplier it already rejected if any of those
options is feasible â and because Alstom has failed to
sufficiently show that none is feasible â I respectfully dissent
from the majorityâs holding that Alstom has standing.41
40
First quoting Oral Arg. Tr. 17; and then JA 130.
41
In addition to its theory of economic injury, Alstom proposes two
other theories of injury â competitive injury, see Appellant Br. 19â
28, and the deprivation of a lawful procurement process, see id. 28â
32. In my view, those two theories fare no better than Alstomâs
economic-injury theory because all three theories depend on the
courtâs ability to redress Alstomâs economic injury.
First, to the extent that Alstomâs theory of competitive injury
survives TransUnionâs holding that an injury must have âa close
relationship to harms traditionally recognized as providing a basis
for lawsuits in American courts,â TransUnion LLC v. Ramirez, 141
S. Ct. 2190, 2204 (2021), its survival probably depends on a link
between the competitive injury and an economic harm like lost
profits, see Air Excursions LLC v. Yellen, 66 F.4th 272, 280 (D.C.
Cir. 2023) (grounding competitive injury in the fact that a plaintiffâs
âbottom line may be adversely affected by the challenged
government actionâ (cleaned up)); PSSI Global Services, LLC v.
FCC, 983 F.3d 1, 11 (D.C. Cir. 2020) (âa party asserting competitor
standing must make a concrete showing that it is in fact likely to
suffer financial injury as a result of the challenged actionâ (cleaned
up)); Mobile Relay Associates v. FCC, 457 F.3d 1, 13â14 (D.C. Cir.
2006) (even a ââdirectâ and âcurrentâ competitorâ may âlack
competitor standingâ if they âfailed to make a concrete showing that
they are likely to suffer financial injuryâ); cf. FCC v. Sanders
Brothers Radio Station, 309 U.S. 470, 477 (1940) (Congress âmay
have been of opinion that one likely to be financially injured by the
issue of a license would be the only person having a sufficient
interest to bringâ suit). And because this court cannot redress
Alstomâs economic injury â for the reasons explained
above â Alstomâs theory of competitive injury fails.
Second, as to the alleged deprivation of a lawful procurement
process, Alstom has not âidentified a close historical or common-law
analogue forâ such an âasserted injury.â TransUnion, 141 S. Ct. at
2204. And because (absent the violation of a constitutional right) the
concrete and traditional harm most likely experienced by those
deprived of a lawful procurement process is their âlost profits,â see
DIRECTV, Inc. v. FCC, 110 F.3d 816, 829 (D.C. Cir. 1997), that
theory too depends on the courtâs ability to redress Alstomâs
economic injury.